Is latest version | Yes |
TSO name | Hellenic Gas Transmission System Operator S.A. |
TSO EIC | 21X-GR-A-A0A0A-G |
Balancing zone | Greece |
Event start | 2020-10-13T06:00:00+02:00 |
Event stop | 2020-10-16T06:00:00+02:00 |
Event status | Active |
Reason of unavailability | 1) Disconnection of old and installation of new Regulating Valves Mokveld at Bordering Metering Station (BMS) Sidirokastro2) Connection to the NNGTS of the Metering/Regulating Station (U6910) at the Interconnection Point between the DESFA and TAP networks at Nea Messimvria |
Type of event | Transmission system unavailability |
Type of unavailability | Planned |
Remark | Transmission Capacity for Delivery at Entry Point 'SIDIROKASTRO': 19.000.000 kWh/Day Transmission Capacity for Reception of Reverse Flow at Exit Point 'SIDIROKASTRO': 0 kWh/DayTransmission Capacity for Delivery at Entry Point 'KIPI': 36.000.000 kWh/Day |
Affected asset or unit (Point name) | 21Z000000000020C |
Affected asset or unit (EIC) | 21Z000000000020C |
Point direction | entry |
Unit of measurement | kWh/d |
Technical capacity | 117804036.00 |
Available capacity | 19000000.00 |
Unavailable capacity | 98804036.00 |
Publication date and time | 2020-09-24T14:22:43+02:00 |