Programming Procedures
Annual Unloading Planning
For the good, reliable, safe and most economic operation of the LNG Facility, the Operator shall prepare an Annual LNG Planning.
The Annual LNG Planning shall be prepared each Year and shall cover each of the following fifteen (15) Years. The LNG Annual Planning shall include cumulatively for each Year to which it relates:
Α. The Annual Schedule of LNG cargo unloading at the LNG Facility during the year (Annual LNG Plan); and
Β. The booking of Bundled LNG Capacity
The Annual LNG Planning shall be conducted through an auction procedure (“LNG Auction”), distinct for each year of the Annual LNG Planning, which shall be conducted using an electronic auction platform, subject to the more specific conditions of the Network Code, the Standard Agreements for Transmission of NG and the Usage of the LNG Facility, the NNGS Tariff Regulation and the LNG Auction Manual. LNG Users who are also Transmission Users are entitled to participate in the LNG Auction.
LNG auctions
In application of the provisions of the NNGS Netwwork Code, the Operator has time windows for the unloading of LNG cargoes, either in series or individually, and booking LNG Capacity, i.e. Delivery Capacity at the Entry Point “Agia Triada” and an equivalent Re-Gasification Capacity at the Revithoussa LNG Terminal, through auctions.
The auctions are held in two phases:
Α. LNG Cargo Unloading Time Windows are available, in accordance with the current RAΑEΥ decision, in two distinct stages:
1) Series of Slots, defined as a specific number of Standard LNG Slots, of one or more categories, offered as an indivisible set; and
2) Individual unloading time windows
Β. Users who have been allocated at least one LNG window in phase A, have the possibility to book LNG Capacity for the whole year (Continuous LNG Capacity), including all or part of the LNG Capacity allocated to them in the first phase of the auction.
Monthly Unloading Planning
For the good, reliable, safe and most economical operation of the LNG Facility, the Operator shall prepare a monthly LNG Cargo unloading Plan, through which the unloading of LNG Cargoes shall be scheduled during the following month (Month M).
For this purpose, each LNG User shall submit to the Operator, through the Electronic Information System, a Monthly LNG Unloading Planning Nomination (Monthly LNG Nomination), no later than twenty-eight (28) days before the beginning of each Month M (Deadline for the submission of Monthly LNG Nominations).
Unscheduled Unloading
Any LNG user wishing to unload LNG cargo during a Month, which has not been included in the Final Monthly LNG Plan for that Month, shall submit a request to the Operator through the Electronic Information System. The request for an Unscheduled LNG Unloading shall be submitted no earlier than 15.00 on the Deadline for the Announcement of the Initial Monthly Plan and no later than one (1) Day prior to the Desired Unloading Date.
The Operator informs the applicant of its decision through the Electronic Information System. Applications, are evaluated by the Operator on a first come first served base.
Please refer to chapter 11 of the Network Code about the procedures of LNG Scheduling